1. Ruby FPSO Topsides
Owner 
Main Contractor
Project Period
Work Description
  : Malaysia International Shipping Company
  : Malaysia Marine and Heavy Engineering Sdn Bhd.
  : May 2009 – February 2010
  : Fabrication, installation and pre-commissioning for electrical, instrumentation and telecommunication works.

   
2. Ruby FPSO - Conversion
Owner 
Main Contractor
Project Period
Work Description
: Malaysia International Shipping Company
: Malaysia Marine and Heavy Engineering Sdn Bhd.
: November 2007 – February 2010
: · Dismantle and Service of E&I Equipments.
  · Calibration and Service of Control Valves.
   

3. Tangga Barat Jacket

Owner 
Main Contractor
Project Period
Work Description
: Petronas Carigali Sdn Bhd
: Malaysia Marine and Heavy Engineering Sdn Bhd
: August 2009 – November 2009
: Installation of Jacket Grouting Tubing System.
   
4. Pluto LNG Topsides
Owner 
Main Contractor
Project Period
Work Description
: Woodsides Burrup Pty Ltd
: Ramunia International Service Ltd.
: August 2008 – October 2009
: Fabrication and installation for electrical, instrumentation and telecommunication works.
   

5. Shell Ethylene Cracker Complex (ECC) Singapore

Owner 
Main Contractor
Project Period
Work Description
: Woodsides Burrup Pty Ltd
: Ramunia International Service Ltd.
: August 2008 – October 2009
: Fabrication and installation for electrical, instrumentation and telecommunication works.
   
6. Dana Mopu 252 Jack-up Rig
Owner 
Main Contractor
Project Period
Work Description
: PTT Exploration and Production Public Company Ltd 
: INE Technologies Sdn Bhd
: January 2009 – July 2009
: Supplied of various materials and provided competent manpower to fabricate and install E&I equipments and devices.

   
7. LNG Tenaga Tiga
Owner 
Main Contractor
Project Period
Work Description
: Malaysia International Shipping Company
: Malaysia Marine and Heavy Engineering Sdn Bhd
: August 2008 – September 2008
: Involved in demolish and reinstall of PAGA System and life boat system.
   
8. NAGA 1 Semi Submersible Rig
Owner 
Main Contractor
Project Period
Work Description
: Japanese Drill Company
: Malaysia Marine and Heavy Engineering Sdn Bhd
: March 2008 – September 2008
: Demolished, serviced and reinstalled for E&I equipments and devices.
   
9. Nang Nuan 252 Jack-up Rig
Owner 
Main Contractor
Project Period
Work Description
: Japanese Drill Company
: Malaysia Marine and Heavy Engineering Sdn Bhd
: March 2008 – September 2008
: Demolished, serviced and reinstalled for E&I equipments and devices.
   
10. PC4 Gas Topsides
Owner 
Main Contractor
Project Period
Work Description
: Petronas Carigali Sdn Bhd
: Malaysia Marine and Heavy Engineering Sdn Bhd
: March 2008 – August 2008
: Involved in fabrication and installation of E&I supports and cable ways.
   
11. Frontier Discoverer
Owner 
Main Contractor
Project Period
Work Description
: Frontier Drilling
: Siqis Ship Management Pte Ltd
: April 2008 – May 2008
: Provided competent manpower to do the maintenances and services for E&I equipments and devices.
   
12. Angel Gas Topsides
Owner 
Main Contractor
Project Period
Work Description
: Woodside Energy Ltd
: Malaysia Marine and Heavy Engineering Sdn Bhd
: November 2007 – February 2008
: Provided competent manpower to complete the outstanding Inspection Test Report (ITR) and Punch List.
   
13. Synthomer Latex Expansion Project KX06 Phase 2
Owner 
Main Contractor
Project Period
Work Description
: Synthomer (Latex) Sdn Bhd
: Rotary Mec (M) Sdn Bhd
: May 2007 – November 2007
: Fabrication, installation ad pre-commissioning for E&I Works.
   
14. Kikeh FPSO Topsides
Owner 
Main Contractor
Project Period
Work Description
: Malaysia Deepwater Floating Terminal (Kikeh) Ltd
: Malaysia Marine and Heavy Engineering Sdn Bhd
: Jun 2007 – October 2007
: Supplied various materials.
   
15. SBM Kikeh Turret
Owner 
Main Contractor
Project Period
Work Description
: Single Buoy Moorings Inc.
: Rotary Mec (M) Sdn. Bhd.
: July 2007 – August 2007
: Supplied materials and provided competent manpower to fabricate and install sample board at offshore.